Elkhart approves up to $45 million to turn the old Chase Bank building into a public safety center
The Daily Elkhart team
If you've walked past the old Chase Bank building at Franklin and Second, it's getting a new job. The Elkhart City Council unanimously passed a resolution Monday night to turn it into a public safety center, and WSBT reports the council approved up to $45 million in borrowing. Police, fire administration and 911 dispatch would move in together.
The resolution caps borrowing at $45 million over up to 20 years
- $45 million
- the most the city could borrow
- 20 years
- the most time the city has to pay it back
- 7%
- the rate in the proposal
Mayor Rod Roberson said it's the first time all three functions would share a building. Police Chief Ray Juengst said the current station wasn't built for today's technology. WNDU says the city plans to keep the old walls and rebuild the inside.
- Remodel cost: under $430 per square foot, Roberson said
- Cost to build new: around $750 per square foot
- Project price tag: around $42 million
- Repaid with: Aeroplex, Cassopolis Street and Technology districts
The project moves from demolition to bids to renovations
- OctoberCouncil approves nearly $2 million for early demolition work.
- Nov. 16Council unanimously passes the resolution on the public safety building.
- Jan. 2027City expects final numbers once the project is bid out in mid-January.
- AprilCity hopes to begin renovations.
The city is still bidding the work out. Roberson said final numbers should come in mid-January, with renovations hopefully starting by April.