Drainage board approves groundwater discharge from Microsoft's data center site into local creeks
The Daily Elkhart team
If you live near Juday Creek, here's a permit to know about. The St. Joseph County Drainage Board approved the plan Monday to pump groundwater off Microsoft's data center site while crews install sewer and water lines. Project applications put the maximum rate at 200,000 gallons per hour into Willow Creek and Juday Creek.
200,000gallons per hour at most, the rate in project applications
The total will depend on how long the pumps run and how much water must be removed.
Source: wndu.com
WSBT reports the work could last about 40 days, with pumping starting in late February and running through April. WNDU says three wells would operate at different times between mid-December and early April, not all at once.
Reports differ on when the groundwater pumping would run
December 2026 to April 2027
2 at once, Feb.–April
Drainage Board member Anthony Hazen said officials don't expect flooding or creek overflow, and that the drilling company plans to put monitors around nearby wells. Steve Francis, vice president of the Juday Lake Estates Homeowners Association, says the project could involve draining nearly 192 million gallons from one area of the site.
“It's a large amount of water. And I know that there's a lot of environmental factors that I'm concerned about.”
- Creek: home to one of Indiana's few trout streams
- Concerns: erosion, pollution and wildlife along roughly 14 miles of creek
- Neighbors on well water worry about their water quality