Amazon's data center near New Carlisle is more than half built or under construction
The Daily Elkhart team
If you follow the Amazon data center west of South Bend, construction is continuing near New Carlisle. Over half of the planned 32 buildings are finished or under construction across three sites. Seven buildings on the north campus are already online and running AI models.
Seven of nine north campus buildings are complete
7 of 9
- north campus buildings complete
- 2 buildings still to come online
Source: inkfreenews.com
View as table
| Count | Share | |
|---|---|---|
| north campus buildings complete | 7 | 78% |
| buildings still to come online | 2 | 22% |
- Jobs: more than 900 full-time hires, most of them Hoosiers
- Size: about 216,000 square feet per building
- Third site: winter may keep work from getting far until spring
- Still ahead: two to three more years of construction, county leaders say
AWS Vice President Josh Weissman said eight of nine south campus buildings are expected to come online in the coming weeks. The last one is targeted for early 2027, and the two remaining north buildings are on track for the first half of 2027. WNDU calls the complex an $11 billion project, while the South Bend Tribune's report puts it at $13.8 billion.
Amazon's data center buildings are set to come online through 2027
- Oct. 2024Construction breaks ground on the data center campus.
- SoonEight of nine south campus buildings are expected to become operational in the coming weeks.
- Early 2027The final south campus building is targeted to come online.
- H1 2027The last two north campus buildings are on track to come online in the first half of 2027.
Source: inkfreenews.com
Sources: WNDU, inkfreenews.com