GrowthSaturday, November 14
Elkhart County's plan commission votes on data center standards as a Penn senior voices concerns
The Daily Elkhart team
Elkhart County's plan commission voted unanimously this week to adopt standards for data center buildings of at least 50,000 square feet, as updates to the county's development ordinance. WVPE reports that St. Joseph and Elkhart county officials are taking differing approaches.
Elkhart County's data center standards would set size, setback and vibration rules
| Standard | Rule |
|---|---|
| Buildings covered | At least 50,000 square feet |
| Setback | At least 250 feet from property lines next to homes or schools |
| Vibrations | Couldn't be detectable off-site |
Source: WVPE
Sounds you can hear couldn't be louder than 60 decibels from 7 a.m. to 7 p.m., or louder than 45 decibels at night.
Data center sound limits would drop from 60 decibels by day to 45 at night
Source: WVPE
View as table
| Value | |
|---|---|
| 7 a.m. to 7 p.m. | 60 dB |
| Night | 45 dB |
Meanwhile, a Penn High School senior is making a trip to share concerns about data centers.
- Home: within one mile of Microsoft's Granger site
- Site: a hyperscale data center
- Destination: San Francisco, with the group We Make Indiana